Cooling Towers in Hong Kong must undergo annual independent audit.

cooling tower EMSD audit process

Cooling Tower Audit Process

The EMSD cooling tower audit requires:

1. An inspection of the cooling tower system;
2. examination of cooling tower records;
3. Provide EMSD with audit report;


The document review shall include examining the relevant documention including the schematic drawing, and the annual record, including

A. water treatment lab results;
B. maintenance records;
C. operating records;


The goal of the audit report is confirmation that the system was operated in accordance with code, and listing any defects discovered.

Kelcroft has conducted Cooling Tower EMSD annual audits, and prepared reports for EMSD in accordance with the EMSD code of practice.

EMSD cooling tower audit process



Call our Hong Kong office today to order your EMSD cooling tower report.